HOME

• About the Watershed
• Watershed FAQ
• Concerns & Issues
• Management Plans
• MDNR Boat Launch
• Public Access Sites

• About the CLWA
• Water Quality
• Education &
Communications
• Zoning & Land Use
• Development
• Ad Hoc & Special
Committees
• Calendar
• Membership Form
• Newsletters
• References
• Watershedware

Selected Web Links
Photographs

Last Revised:
7-22-2012

© Copyright
2004-2012
by the Crystal Lake
& Watershed
Association and
ATI Consulting

All photos © Copyright
2010
– Crystal Lake
& Watershed Association


All Rights Reserved.

Site Meter

Crystal Lake and Watershed Association

 

Crystal Lake &
Watershed Association
P.O. Box 89, Beulah, MI 49617
Phone: (231) 882-4001
FAX: (231) 882-7810
Email Us
Follow us on Facebook

Mollineaux Road Boat
Launch Photographs


July 2012 — Site Complete


Fishermen prepare to head out on Crystal Lake from DNR’s Mollineaux Road boat launch.



November 2011 — Paving Begins


Work crews from Rieth-Riley Co. apply a top layer of asphalt to the Crystal Lake boat launch
area, adjacent to guard rails that will protect a section of the Betsie Valley Trail.



Paving equipment begins working its way up the hill from the
launch site to the parking area on Nov. 6, 2011.

August 2011 — Work through the summer


Stairway

Workers are well along on the framing for the long stairway that will ascend the hill between
the launch ramps on the Crystal Lake shoreline and the parking area 80 feet above.
The finished stairway will consist of composite decking on treated wood framing members,
atop steel pilings driven into the earth.


Sidewalk

Workers from Reith-Riley Construction on Aug. 25 put finishing touches on a section
of concrete sidewalk in the upper parking area. The large parking lots have been
excavated, leveled and layered with gravel. Paving will be scheduled for late summer or fall.


Road Work

The main access road has been excavated down the hillside from the upper parking area
to the launch ramps on the Crystal Lake shore. As of Aug. 25, crews were using
heavy equipment to install manholes and drain tiles to handle rainfall and storm water.
Still to come on the hillside are additional fill material, concrete curbs, paving and
revegetation. The contractor and state officials expect the work to be completed this fall.


Launch Site

The actual site of the launch ramps, seen here from the location of the hillside stairway, has
been cleared of trees and vegetation. As of Aug. 25, construction crews were still working on
underground drainage structures. The Betsie Valley Trail has been left in place across the site
temporarily to allow bicycle access and to act as a “dam” to prevent silt from reaching
Crystal Lake. The trail will soon be realigned across the back of the site. Dredging of the
lake bottom to a depth of four feet is scheduled to begin the last full week of August.



November 2010 — Intersection paved



Mollineaux Road / M-115 Intersecion

Crews from Reith-Riley Construction Co. paved the realigned intersection of Mollineaux Road
and M-115 on Nov. 2, 2010. The road should be reopened to traffic within a few days.
The new intersection is the first stage in construction of a new public boating access
site on Crystal Lake. The entrance to the new access site will be from Mollineaux road.
The entire project is expected to be completed in the spring of 2011.






August 2010 — Construction begins


Boat Launch — Mollineaux Road

The Y-shaped intersection of Mollineaux Road and M-115 in Benzonia Township is to be
rebuilt as part of the Michigan DNR's Crystal Lake Boat Launch project. Mollineaux (on the right
in this photo) will be curved around to create a right angle turn. Road construction work is to
commence about Aug. 25, and will take up to four weeks. Mollineaux Road will be closed at the
intersection for a portion of the time. Under the court agreement entered last spring, the
contractor must complete work on the intersection before beginning construction of the launch
itself. Until the road construction is done, activity on the interior of the site will be limited to such
things as brush cutting, surveying, setting up silt fences, relocating power lines, and other tasks
that are a necessary part of the road reconstruction.



Boat Launch — Clearing

Work has begun on construction of a state boat launch on the South Shore of Crystal Lake.
On Aug. 17, crews started clearing brush at the site, near Mollineaux Road and M-115. The
contractor expects to start soon on excavating the roadside at the intersection of Mollineaux
Road and M-115.




Boat Launch — Betsie Valley Bike Trail

In this photo, riders pass the Crystal Lake Boat Launch site on the Betsie Valley Trail. The
popular hiking and bicycling trail is to remain open during the construction period, according
to the Michigan Department of Natural Resources and Environment. Trail users may encounter
some delays in the fall, when excavation begins along the lake shore. As part of the boat launch
project, a short section of the bike trail will be rebuilt as a boardwalk across a wetland on the site.


Boat Launch — Crystal Lake Shoreline

Changes will be coming soon to this quiet stretch of Crystal Lake shoreline. Contractors for the
Michigan Department of Natural Resources and Environment have begun work on a major new
boat launch that is expected to be completed on this site in the spring of 2011.


HOME

About the Watershed

Watershed FAQ

Concerns & Issues


Management Plan
s

MDNR Boat Launch

Public Access Sites
About the CLWA

• Water Quality

•
Education & Communications

• Zoning & Land Use

• Development

• Ad Hoc & Special Committees

• Calendar
• Membership Form

• Newsletters

• References

• Watershedware

Selected Web Links

Photographs